The Georgia DOT (GDOT) is seeking feedback on the proposed widening and reconstruction of Dahlonega Highway, to include three roundabouts, in North Hall from Price Road to Yellow Creek Road near Murrayville.
GDOT says the goal is to “improve safety and…reduce current and future congestion along the corridor.”
The timetable for the project along with the cost of each component:
Project Phase | Amount | Fiscal Year |
Preliminary Engineering, Scoping | $14,476,274.40 | 2023 |
Right of Way | $26,368,000.00 | 2027 |
Construction | $66,653,052.64 | 2030 |
Utilities | $6,250,017.38 | 2030 |
Total | $113,747,344.42 |
- Project proposes to add roundabouts at three locations along the corridor at Elrod Road, Hubert Stephens Road/Fieldale Farms Driveway, and Kanaday Road/Old Dahlonega Road; studies have shown roundabouts reduce crashes and improve operations by eliminating crossing conflicts and reduce delay when compared to a signalized intersection.
- Add sidewalks
GDOT invites the public to provide comments by May 23.
Click here for more details about the plans and also instructions, at the bottom of the page, on high you comment.